An ECC contract's records kept with the programme: Completion and Key Dates mapped to the activities that achieve them, programme submissions and replies, early warnings, instructions and compensation events with their clocks, a compensation event's time impact, and the clause 31 and 32 checks.


What it gives you
Every Key Date and Completion shown against the date P6 shows for it, in the open programme, the Accepted Programme and every update.
Notice periods and reply clocks run from the dates you record, and What is due lists every one against today.
A compensation event's fragnet is recalculated with and without it, giving the movement in Completion and each Key Date in working days.
From early warning to outcome
A funnel follows each compensation event back through its early warnings and instructions and on to its quotation and outcome. Clicking an event highlights its activities in the Gantt and on the time-chainage chart.
An assessment aid, not an acceptance
Nothing here moves the Completion Date, and a link or a reminder decides nothing: entitlement, notices and implementation stay with the people who make them. Where a check relies on activity names and nothing matches, it is to be checked by hand, not failed.
| Clause | Items |
|---|---|
| 31.2 | Starting date · access dates · Key Dates · Completion Date and planned Completion · order and timing of operations · work of the Client and Others · provisions for float · time risk allowances · dates needed for access, acceptances, Client-provided Plant and Materials and information from Others · resources · health and safety (by hand) · other Scope information (by hand) |
| 31.3 | Plans shown are practicable · shows the information required · represents the plans realistically · complies with the Scope (by hand) |
| 32.1 | Actual progress · effect on remaining work · compensation events · delays and notified Defects · other changes to the Accepted Programme |
| 32.2 | Revised programmes at the stated interval |
Check your next update before anyone else does.
Free for a day. Export an XER from P6 and see what it says.