Skip to content
P6 Schedule Analyticsby PlanAssure
Analyse

Critical path and Gantt

Included in: Every paid plan, and the trial

An independent forward and backward pass in real dates. Each activity advances on its own calendar and each lag on its predecessor's, completed work is pinned to its actual dates, and the Gantt shows the result in the layout planners already read, with the baseline beneath every bar.

Gantt in P6's layout: WBS bands, actual bars to the data date, critical work in red.
Critical path and Gantt · demo programme Rev 6

What it gives you

Live from the demo

The path that drives Completion, tie by tie.

The last links of the demo programme's driving path: Section 3 back in service, the access tracks reinstated, snagging and handover, then Completion. Driving ties carry the light; dashed ties feed in with float to spare. Each box shows its total float in working days: the whole path is late.

In the app, the logic trace opens from any activity and follows its drivers up and its successors down, laid out by the same dagre engine as this drawing.

Logic trace · driving path to PM-1090 Completion
The last activities on the demo programme's driving path, from Section 3 pre-commissioning through handover to Completion, with the ties that feed them and their total float.S3-4010 Section 3 pre-commissioning t… · finish 6 Dec 2026 · total float -16 daysS3-4010-16dSection 3 pre-commissioning t…S3-4020 Section 3 return to service -… · finish 6 Dec 2026 · total float -16 days◆ S3-4020-16dSection 3 return to service -…S3-5010 Reinstate access track T53-T56 · finish 8 Dec 2026 · total float -13 daysS3-5010-13dReinstate access track T53-T56S3-5030 Reinstate access track T61-T64 · finish 10 Dec 2026 · total float -13 daysS3-5030-13dReinstate access track T61-T64S3-5050 Reinstate access track T69-T71 · finish 12 Dec 2026 · total float -13 daysS3-5050-13dReinstate access track T69-T71HO-6010 Rectification of defects list… · finish 18 Dec 2026 · total float -10 daysHO-6010-10dRectification of defects list…HO-6020 Handover of the works to the… · finish 18 Dec 2026 · total float -10 days◆ HO-6020-10dHandover of the works to the…HO-6030 Time risk allowance before Co… · finish 15 Jan 2027 · total float -10 daysHO-6030-10dTime risk allowance before Co…PM-1090 Completion · finish 15 Jan 2027 · total float -10 days◆ PM-1090-10dCompletionS3-4000 Section 3 post-stringing line… · finish 4 Dec 2026 · total float -16 daysS3-4000-16dSection 3 post-stringing line…S3-1215 Dismantle scaffold at B-road… · finish 4 Dec 2026 · total float -14 daysS3-1215-14dDismantle scaffold at B-road…PM-1030 Key Date 3 - Section 3 energi… · finish 6 Dec 2026 · total float -16 days◆ PM-1030-16dKey Date 3 - Section 3 energi…S3-5040 Reinstate access track T65-T68 · finish 12 Dec 2026 · total float -13 daysS3-5040-13dReinstate access track T65-T68S2-5050 Reinstate access track T45-T48 · finish 12 Nov 2026 · total float 13 daysS2-5050+13dReinstate access track T45-T48HO-6000 As-built records and O&M manu… · finish 18 Dec 2026 · total float -10 daysHO-6000-10dAs-built records and O&M manu…
Driving tie Feeding tieFigures: total float in working days

Why recompute at all

An export carries whatever late dates were stored at the last F9. If the file wasn't rescheduled against its data date, those dates describe a plan that no longer exists. The engine detects this, recomputes float from the network, and tells you which basis it used.

The Gantt, as P6 draws it

  • Collapsible WBS tree with summary bars; ID, name, remaining duration, start, finish and total float.
  • Blue actual to the data date, green remaining, red when critical, with the planned or baseline dates as a thin bar underneath.
  • Time risk allowances hatched, read from their names or the contract's own convention.
  • Weeks, months, quarters, years or fit, and a jump to the data date.

Check your next update before anyone else does.

Free for a day. Export an XER from P6 and see what it says.