Skip to content
P6 Schedule Analyticsby PlanAssure
Analyse

Earned value and earned schedule

Included in: Every paid plan, and the trial

The Earned Value tab reports every measure EIA-748 names, worked out the way P6 works them out: budgets from the baseline, earned value by each WBS element's own technique, and the forecast the way P6 forecasts. Every figure was checked against P6's own on a project using each technique.

Earned Value: six cards for scope, SPI, CPI, CSI, EAC and TCPI, each with its status in words and a six-period trend.
Earned value and earned schedule · demo programme Rev 6

What it gives you

Live from the demo

The S-curve, as the Earned Value tab draws it.

Planned, earned and actual cost month by month to the data date, and the forecast to Completion beyond it. These are the engine's figures for the fictional overhead line programme: SPI 0.93, CPI 0.99.

Earned Value · cumulative cost S-curve · data date 30 Jun 2026SPI 0.93 · CPI 0.99

At the data date the demo programme has earned £4,007,739 against £4,296,067.41 planned, for an actual cost of £4,030,260.52.

Planned value Earned value Actual cost ForecastHover for the month's figures

Read the way P6 holds it

  • BAC is each activity's baseline budget: resource assignments and project expenses, in money or labour hours.
  • Earned value follows the technique each WBS element sets in P6: activity % complete, 0/100, 50/50 or a custom %.
  • ETC is P6's remaining cost, or the work left times a performance factor. EAC is AC plus ETC, as P6 works it.
  • Money is shown in the currency you view in, at the file's own exchange rates, as P6 shows it.

One page for the whole story

  • Six cards (scope, SPI with SPI(t), CPI, CSI, EAC and TCPI), each with its status in words and a six-period trend.
  • The S-curve with the forecast from the data date to EAC, and the period's planned, earned and spent on one time axis.
  • Click a control account anywhere and the curve, the cards and the table narrow to it.
Measures as implemented
MeasureHow it is worked out
BACΣ baseline budget of assignments and expenses (the activity's own budget where it has neither)
PVBAC spread over the baseline's planned dates to the data date
EVBAC × performance % complete, by the WBS element's earned value technique
ACΣ actuals on assignments and expenses
ETC · EACP6's remaining cost, or (BAC − EV) × a performance factor · AC + ETC
SV · CV · VACEV − PV · EV − AC · BAC − EAC
SPI · CPI · CSIEV ÷ PV · EV ÷ AC · CPI × SPI
TCPI(BAC − EV) ÷ (EAC − AC), as P6 shows it; towards BAC alongside
SPI(t) · SV(t)Earned schedule ÷ actual time · ES − AT, in working days

Check your next update before anyone else does.

Free for a day. Export an XER from P6 and see what it says.