Skip to content
P6 Schedule Analyticsby PlanAssure

Account and help

Glossary

Planning, DCMA and earned value terms as this app uses them.

Terms as this app uses them.

TermMeaning
AC (ACWP)Actual cost of work performed: what the work done so far cost.
ATActual time: working days from the start to the data date.
BACBudget at completion: the total budget of the work.
BaselineA saved version of the programme to measure against. Where the export carries none, P6's planned dates stand in.
BEIBaseline execution index: activities completed ÷ activities planned to be complete by the data date.
CalendarThe working days and hours an activity works to. Each activity advances on its own calendar.
CPICost performance index: EV ÷ AC. Below 1.0 is over budget.
CPLICritical path length index: (critical path length + total float) ÷ critical path length.
Critical pathThe longest chain of logic to completion; a delay on it delays the finish.
Data dateThe date progress was measured to. Actuals are before it; remaining work after it.
DCMA 14-pointA standard set of schedule quality checks, originally from the US Defense Contract Management Agency.
Dangling logicAn activity's start or finish that nothing controls, such as an SS-only successor with no finish tie.
EACEstimate at completion: BAC ÷ CPI.
Earned Schedule (ES)The date by which today's earned value should have been earned, in working days from the start.
EV (BCWP)Earned value: budget × percent complete.
F9P6's schedule command, which recalculates dates and float from the data date.
Free floatHow far an activity can slip without delaying any successor.
Hard constraintA constraint that fixes or caps a date: Mandatory, Start/Finish On, Start/Finish On or Before.
Hit rateOf the work an update said would finish before the next data date, the share that did.
Key DateAn NEC4 date by which the Contractor meets a stated condition.
Lag / leadA wait on a relationship. A lead is a negative lag.
LOELevel of effort: an activity whose dates follow the work it spans.
Negative floatThe plan can't meet a date it's held to.
Not statusedOpen work whose dates are already past without actuals.
Open endAn activity missing a predecessor or a successor.
Out of sequenceProgress recorded on an activity before its logic allowed it to start.
P-date (P50, P80)The finish date a risk simulation met in that percentage of runs.
PV (BCWS)Planned value: budget due by the data date on the planned dates.
QSRAQuantitative schedule risk analysis: a Monte Carlo simulation of the finish.
Retained LogicP6 option keeping remaining work behind its unfinished predecessors.
Slippage rateDays the forecast finish moved per day elapsed between updates.
SPI / SPI(t)Schedule performance index, by cost (EV ÷ PV) and by time (ES ÷ AT).
Terminal floatUnder NEC4, the time between planned Completion and the Completion Date.
Total floatHow far an activity can slip without delaying the finish or a constrained date.
TCPITo-complete performance index: the efficiency the rest must achieve to meet budget.
Time risk allowanceUnder NEC4, time the Contractor shows in the programme for risk.
XERPrimavera P6's native export format. P6 XML is the other supported export.